Work by room or zone
Reconcile quantity and location before judging finish or function.
YUESHANDECODesign-led custom furniture & FF&E delivery partner in ChinaSubmit a project ↗Run a room- or zone-based FF&E pre-punch with item IDs, issue types, photos, responsibility and closeout tracking. What survives the walk becomes the handover and spares record; keep the evidence in the inspection file.
A pre-punch turns final inspection into a controlled room- or zone-based process before the formal walk. Tie every issue to an item ID, location, defect or missing-work category, photo reference, responsible party, due date and status. Distinguish manufacturing defects, transit damage, installation issues and damage by other trades.
Decision guide
Reconcile quantity and location before judging finish or function.
Manufacturing, transit, installation and site damage require different evidence and owners.
A correction is not closed until the item is rechecked and the status is recorded.
Create one traceable issue record instead of repeating unstructured site walks. This checklist does not replace contractual inspection or guarantee acceptance. For the commercial decision this tool supports, review the quality-control scope.
Last reviewed: August 28, 2026
Condition record · custody · closeout
A clean handover begins before shipping. The team needs item identity, approved reference, packing and condition evidence, custody records, receiving exceptions, corrective action and a usable spare-parts and maintenance record.
| Control point | What the receiving team needs | Record to retain |
|---|---|---|
| Before packing | Released item, quantity and visible condition | Inspection status, photographs, item/room code and package plan |
| Transfer of custody | Package count, labels and handling condition | Packing list, loading record and transport document references |
| Receiving | Visible and concealed condition, shortages and wrong items | Dated photographs, exception notes, quarantine and claim reference |
| Closeout | Resolved defects and items needed for operation | Punch status, replacement log, care data, warranties and spares register |
Latest drawing or rendering, quantities, intended use, destination, material references, current quotation assumptions and unresolved comments.
Approved revision, sample identity, decision limits, exceptions, responsible party and the evidence required before the next release.
Record scope, revision, decision, approver, exceptions, corrective action and release status in the project log.
Only when the approval states what was reviewed. Colour approval alone does not approve structure, comfort, dimensions or the entire production batch.