01

Final inventory and item IDs

Reconcile ordered, delivered, installed, spare and missing quantities by item and location. Keep the identifier used in drawings, QC and packing.

02

Warranties and supplier records

Record supplier, contact, warranty scope, start date, exclusions and the evidence needed to raise an issue. The standard position is one year from acceptance with lifetime maintenance support, and a complete claim is acknowledged within 24 hours; state the named contact that receives it.

03

Finish codes and care

Provide approved finish, textile, leather, stone and hardware references together with cleaning and maintenance instructions.

04

Spare hardware and attic stock

Agree project-specific quantities for glides, hinges, handles, touch-up material, extra textile or leather and replacement components. Fixings are the fixed line: screws, cam locks, dowels and brackets are packed at 3% of the quantity used.

05

Retained samples and open punch

State where control samples are stored and carry every unresolved item with owner, action, due date and status into closeout.

06

Replacement strategy and sign-off

Document how future replacements will be identified, ordered, colour-matched and approved; obtain a clear handover record from the receiving party.

Place handover and spares inside the FF&E scope ↗

07

What should a usable handover pack contain?

Build the directory before the final delivery, not after the operator asks for a replacement. Use the same item codes as the approved schedule and identify which documents are final versus still awaiting confirmation.

  • Final item/location inventory with delivered, installed, missing and spare quantities.
  • Approved material, finish and supplier product references; retained-sample location.
  • Assembly, care and maintenance instructions for the selected products.
  • Actual warranty terms — one year from acceptance, with lifetime maintenance support — and the named contact that acknowledges a claim within 24 hours.
  • Spare-part identifiers, agreed quantities, physical storage location and custodian.
  • Open issue register with action owner, due date, evidence and closure decision.

Keep finish and product codes tied to the specification ↗

08

How much attic stock should the project order?

Agree quantities by component, exposure, replacement difficulty, storage conditions and operator preference. There is no universal percentage, because the package was made for this project rather than drawn from a catalogue, and a repeatable glide and a selected stone top do not need the same spare strategy. The exception is fixings: screws, cam locks, dowels and brackets are packed at 3% of the quantity used, since they are consumed on site and a missing one stops the assembly. Record whether the allowance is included in the order, separately priced or excluded.

Ask how future replacements will be identified and whether a retained finish reference can support matching. Do not promise identical future batches or permanent product availability. Label physical spares and record where they are stored so the inventory is usable after the project team leaves.

Include agreed spares in quotation scope ↗

09

When is handover actually complete?

Separate delivery receipt, installation completion, document receipt and closure of outstanding items. Agree the relevant acceptance criteria and authorized decision maker for each. A handover pack may be received while specific actions remain open; show that status rather than claiming the whole package is complete.

At the final review, reconcile each missing or damaged item with the receiving register and record the accepted remedy. Schedule follow-up actions with the operator and preserve the final revision of the pack. Include time for this review in the project plan instead of treating opening day as a documentation deadline with no allowance.

Reconcile the receiving exceptions ↗

Allow time for closeout before the ready date ↗

Agree the project handover scope ↗

Send the handover requirements for review ↗

10

Where the delivery checklist ends and the warranty begins

The sections above close the package: inventory, item codes, approved references, retained samples, spares and open items. A warranty register is a different document. It starts when an item is accepted, not when it is delivered, and it is judged against the condition it was accepted in. Keeping the two registers separate stops a delivery exception being treated as a warranty claim, and stops a manufacturing defect being closed as a receiving note.

The link between them is evidence. A claim can only be assessed when the item code, the approved finish reference, the retained sample and the handover condition record can be produced together. That is why this page asks for both registers instead of one combined closeout file.

11

What the warranty covers, and what it does not

The standard YUESHAN position is a one-year warranty with lifetime maintenance support. The proposal for the actual project states the exact coverage, the exclusions and any product-specific conditions, because the answer differs between a bespoke upholstered piece, a stone-topped table and sourced equipment. Treat the proposal wording as the operative text and this page as the framework for checking it.

Coverage is normally directed at manufacturing and workmanship: structure, joinery, upholstery build-up, finish adhesion and hardware function under intended use. It is not a maintenance contract. Movement and colour change from humidity, fading from daylight, wear from cleaning agents, damage from site handling or later modification by another party, and use outside the approved specification are not manufacturing faults. Record that boundary in the register rather than discovering it during a dispute.

  • Manufacturing and workmanship scope stated by product or category.
  • Exclusions listed by cause, not implied.
  • Coverage start point and any limitation period written down.
  • What the buyer must do to keep the coverage valid.
12

Response: how a claim is raised and answered

A claim should enter through one named route with enough information to assess it first time: item code and quantity affected, location, date of acceptance, photographs of the item and the affected detail, the approved reference it was measured against, and the action already taken to protect the item. A complete claim is acknowledged within 24 hours. An incomplete one gets a request for information instead, which is why the record set matters more than the wording of the complaint.

The assessment steps and any on-site inspection arrangement are stated in the proposal or the service agreement for that project, because an inspection that is practical in one city is not practical in another. Where the product is in a live hotel or a residence in use, the practical question is usually whether an interim measure is needed before a final remedy is agreed. Record the interim step and its owner, then record the remedy separately: repair, replacement, missing-part supply or further review. Each remedy gets a target date and an acceptance record.

Separate transit damage from an in-service claim ↗

13

Spare parts and replacement after the warranty period

Lifetime maintenance support means the item can still be identified and repaired after coverage ends; it does not mean free replacement for the life of the product. What makes that support usable is the record set: component identifiers, the original finish and material references, and the agreed spare quantities held at handover. A retained sample is what allows a later replacement to be matched rather than guessed.

Plan replacement by component rather than by item. Glides, hinges, handles, touch-up material, extra textile or leather and selected hardware can be held economically; a stone top or an upholstered frame cannot be held for every eventuality. State which is which in the handover pack, where the spares are stored and who controls them, so the operator is not searching a warehouse after the project team has left.

Because the furniture is made for the project rather than selected from a catalogue, there is no general spare percentage that can be applied across a package. The one allowance that does carry a number is mechanical: screws, cam locks, dowels and brackets are packed as a 3% spare pack against the quantity used. They are fitted on site, they go missing in the process, and a single missing screw stops a wardrobe being assembled while a spare one costs almost nothing.

  • Component-level spare list with agreed quantities and storage location.
  • Fixings packed at 3% of the quantity used, issued with the order.
  • Retained sample and approved reference for colour and texture matching.
  • Replacement lead time and approval route for repeat production.
  • The party responsible for holding and issuing spares.

Review the agreed handover and support scope ↗

Read the published trade and warranty terms ↗

14

Setting a spare quantity by component, not by a percentage of the order

There is no defensible universal spare percentage, and a number invented for a proposal becomes a commitment. The workable method sizes the allowance per component against four questions: how often it fails, how visible the failure is, how long a replacement takes to arrive, and how much disruption it causes while it is missing. A glide that fails quietly and costs cents needs a generous count. A stone top that fails rarely, costs a great deal and takes weeks needs a different treatment entirely.

A practical method is to list components by replacement difficulty and failure frequency, then set a count per room block rather than per project. Handles, glides, hinges, touch-up material and fixings are cheap to hold and expensive to be without. Upholstery fabric and leather are held as a roll length or a hide count tied to the dye lot and to the number of seats using that article. Stone, glass and large finished panels are usually not held: they are re-ordered, and the allowance becomes a documented lead time rather than physical stock.

One allowance does carry a fixed number. Screws, cam locks, dowels, brackets and the small connecting parts are packed as a 3% spare pack against the quantity used. These are consumed and lost during site assembly rather than failing in service, and a single missing screw stops a wardrobe being built, so the pack is issued with the order instead of being argued about after the fact. Everything else here is made for the project rather than selected from stock, which is why no other percentage can be carried from one project to the next.

Whatever the count, write three things into the handover pack: the quantity, where it is held, and who controls it. A spare that exists somewhere in a warehouse nobody can access is not an allowance.

  • Component list ranked by failure frequency and replacement difficulty
  • Quantity basis stated per component: per hundred rooms, per article, or per seat
  • Fixings — screws, cam locks, dowels, brackets — packed at 3% of the quantity used
  • Fabric and leather held by dye lot and tied to the articles actually used
  • Items not held, with the re-order lead time written down instead
  • Physical storage location and the named custodian
  • Whether the allowance sits inside the order, is separately priced, or is excluded

Show the agreed spares inside the quoted scope ↗

15

What spare parts availability actually means after the project closes

Availability is a commitment about time, not about willingness. When an operator asks whether a part can be supplied, the useful answer names the component, how it is identified, the lead time and the minimum order. A part that can be identified but takes twelve weeks is a different proposition from one that ships in a week, and both differ from a part that cannot be identified at all because the item code and finish reference were never recorded.

Two things make later supply possible. Identification comes first: a component reference, the original finish and material reference, and a retained sample that lets a later batch be matched rather than guessed. The re-order route comes second: whether the factory will produce a small repeat batch, at what minimum quantity, on what price basis, and how long it takes. Repeat production is not a spare part. It is a small order, and it is priced as one.

State which category each item falls into in the handover pack. Hardware and standard components are supplied from stock. Upholstery and finish matching depend on the retained sample, and a dye lot may not repeat exactly. Bespoke components and stone are made to order. Writing that down prevents the most common expectation failure, which is an operator expecting a bespoke component to arrive like a catalogue part.

  • Component identification method, so a later request can name the part
  • Lead time stated by category: stock item, repeat batch, or made to order
  • Minimum order for a repeat batch, and where the real constraint sits — usually the material, not the assembly
  • Finish matching route, and the retained sample that supports it
  • Which parts are stocked, which are made to order, and which are not supported

Read the published warranty and support terms ↗

Continue the decision path

Related FF&E resources

Delivery, receiving & closeout: guides and tools ↗Selected project portfolios ↗Export packaging guide ↗Submit a project ↗Browse all FF&E guides ↗

Prepare the Handover Pack

There is no universal spare percentage; quantities depend on the product, project and operator agreement. Fixings are the exception — screws, cam locks, dowels and brackets are packed at 3% of the quantity used.