Make the decision in this order
- Map product and route hazards
- Protect faces, edges, corners and projections
- Restrain hardware and detachable parts
- Engineer stone, glass and heavy components
- Review moisture, stacking and handling
- Validate changed products or packages where needed
What the specification or approval should record
- Packed dimensions, weight and centre of gravity
- Layer-by-layer packing specification
- Corner, face and hardware protection
- Crate, carton, pallet and forklift provisions
- Labels, item codes and opening instructions
- Packing photos, inspection or test reference
Evidence before claim
Use packing drawings, real pack-out photos and any applicable test record for the exact product-package system.
Claim boundary: Do not write ISTA tested or certified unless the exact package has documented testing.
Packing is part of the delivered package, not an afterthought added at the port. Where packaging and inspection release sit in the FF&E lifecycle shows the sequence.
Knock-down or assembled: the choice that moves cost, damage and site labour
Packing format is decided at the drawing stage, not at the packing bench. A knock-down item ships in a smaller cube and usually costs less in freight, but it moves assembly to the destination and puts joint quality in the hands of whoever assembles it. An assembled item protects its own geometry and arrives ready to place, and costs more per cubic metre with more damage risk at the corners.
A hotel package usually splits along the item type. Casegoods and wardrobes travel knock-down or semi knock-down with cam, dowel or bolt-together joints, because the cube saving across hundreds of rooms is substantial and the assembly is repetitive enough to control. Upholstery travels assembled, because a compressed or inverted frame does not recover its shape. Stone tops travel separately, crated on edge, and are fitted on site. Long counters and continuous runs are made in modules with a designed joint, because a single piece will not pass the door.
Whatever the format, the packing has to carry the assembly information. A knock-down piece without a labelled parts list, a hardware pack tied to its item and an instruction sheet becomes a site problem, and the site's answer is usually a telephone call and a delay.
| Format | Freight effect | Where the risk moves | Suits |
|---|---|---|---|
| Assembled | Highest cube per item | Damage in transit and at the door | Upholstery, small tables, fragile geometry |
| Semi knock-down | Moderate saving | Joint alignment and loose hardware | Wardrobes, large casegoods with removable tops |
| Full knock-down | Largest saving | Assembly quality and missing parts at site | Repeat room packages with controlled site labour |
| Modular with designed joint | Moderate | Joint line visibility and alignment | Long counters, continuous runs, items wider than the door |
Loading a container is a plan, not a packing preference
Container loading is decided by cubic volume, then weight, then the unloading sequence. The cubic figure comes from the packed carton rather than the product, and it is the number that decides how many rooms fit into a 40 foot high cube. A package planned on product volume and packed on carton volume will overrun the container, and the overrun is discovered at the port rather than in the factory.
Two limits sit beside the volume. Payload is the first: dense items such as stone-topped tables and metal bases can reach the weight limit before the cube limit. The loading sequence is the second, and it has to match the unloading sequence at the destination. If the first room's furniture sits at the back of the container, every later delivery pays for it. Load by room or by floor, mark the cartons to match, and keep the loading plan with the shipping documents.
Damage in export furniture concentrates at corners, at the base of a stack, and wherever a heavy item sits over a light one. Corner protection, edge boards, a declared stack limit and a floor-loaded or palletised decision all belong in the packing specification, and the loading plan should show where the heavy items sit rather than leaving that to the loader on the day.
- Packed carton dimensions and cube per item, not product dimensions
- Total payload checked against the container limit before the booking is made
- Loading sequence matched to the room or floor unloading sequence
- Carton marks matching the item code and the room schedule
- Stack limit, and the maximum weight the bottom carton may carry
- Heavy items positioned over the floor or the axle line, never over light cartons
- Loading photographs and a signed loading record kept with the shipping documents
Once external carton dimensions are known, use the packed furniture volume calculator to estimate CBM. Stacking, payload and mixed carton sizes still need a loading plan.
Review a Packing Plan
Send the current drawing, BOQ, sample reference or supplier proposal. We will identify the fields that still need a project decision.
Submit your project for review ↗Sources
External standards and product data can change. Verify the current requirement for the product, destination and project.