Name the DDP place and version
Write the precise destination and the agreed Incoterms® version. ‘DDP your country’ is not enough to plan the delivery point or compare offers.
Lock product and specification
Reference item schedule, quantity, dimensions, materials, finishes, drawings and approved samples. DDP does not cure an incomplete product description.
Packing and inspection
State packing method, labels, room codes, pre-shipment inspection access and the release process.
Included and excluded charges
Clarify delivery location, unloading, storage, waiting time, difficult access, installation and packaging disposal rather than assuming every service is included.
Documents and importer information
List the documents the transaction and destination need, then confirm the parties responsible for information and filings with qualified trade providers.
Changes, delay and claims
Define approvals, price or schedule changes, damage evidence and dispute process in the agreement; Incoterms do not cover every sale condition.
Does DDP include unloading and installation?
Under DDP Incoterms® 2020, delivery is at the agreed destination point with the goods ready for unloading; the seller handles import clearance and applicable duties. Unloading and room installation are separate matters to clarify, not benefits to infer from ‘door to door’. Confirm local feasibility with the appointed trade professional before accepting the term.
Write the precise receiving point, vehicle access, unloading resources, appointment, receiving contact and any onward movement to rooms. Ask how waiting, failed access or unavailable storage will be handled. This checklist organizes a discussion; it is not a substitute for transaction-specific contract advice.
What should the buyer send before importing a furniture package?
Send the item/quantity schedule, specification revision, packing assumptions, full destination and required ready date. For a container-sized package, identify split deliveries, room sequence, unloading equipment and storage capacity. For outdoor furniture, confirm the product specification separately: a shipping term does not establish suitability for outdoor use.
- Ask the seller to identify the scope of the DDP offer and any exclusions in writing.
- Confirm who supplies the commercial invoice, packing list and shipment references, and who verifies destination filings.
- Keep estimated transit, customs, appointment and site allowances separate from production duration.
Which records should be ready before dispatch?
Agree carton/item coding, the quantity reconciliation, pre-dispatch condition records and the receiving contact. Decide how exceptions will be reported and who will keep the documents. A delivery signature and final project acceptance are not interchangeable records.
Before deposit or order confirmation, identify unresolved shipping assumptions and the person who must resolve each one. Before dispatch, revisit the list against the actual site and shipment information; do not assume the original target date proves readiness.
Consolidation, warehousing and what DDP does not settle at the destination
A multi-supplier FF&E package usually has to be consolidated before it ships, and consolidation creates its own risk: goods from several factories arrive at one point, are checked against several schedules, and are then loaded together. Decide who consolidates, where, and against which packing list. If the factories ship directly to the port, the container is loaded from several deliveries and the loading sequence stops matching the room sequence.
Warehousing is the second gap. Standard supply terms exclude storage, which means a container arriving before the site is ready has no owner for its cost, its insurance or its condition. Storage can sit at origin before shipment, at the destination port, or on site. Each has a different cost, a different level of protection and a different point at which responsibility moves. Write down which one applies, how long it is covered, and who pays beyond that period.
DDP changes the delivery obligation, not the storage arrangement. The term makes the seller responsible for import clearance and delivery to the agreed place, and nothing in it creates free storage at the destination or makes the seller responsible for a site that cannot receive the goods. A failed delivery appointment, a vehicle that cannot access the site and goods with nowhere to go are chargeable events unless the proposal says otherwise.
- Who consolidates, at which location, and against which packing list
- Whether the container is loaded from one factory or from several deliveries
- Storage location, duration and cost, at origin, at destination port and on site
- Insurance cover during storage, and which party holds it
- What happens, and who pays, when the site cannot receive on the booked date
- Condition recorded at each storage handoff, not only at final delivery
The document set that has to be complete before the container sails
The document set is decided by the destination and the payment method, not by habit. A typical furniture shipment needs a commercial invoice, a packing list that reconciles to the item and room schedule, a bill of lading or sea waybill, and a certificate of origin where the destination grants preferential treatment or the buyer's bank requires one. Timber packing needs heat-treatment or fumigation evidence and ISPM 15 marking where the destination enforces it. Where the goods contain regulated materials, the destination may also ask for a conformity declaration, a test report or a safety data sheet.
The failure mode is almost always the same. The packing list and the invoice disagree on quantity or description, or the item codes on the packing list do not reconcile to the schedule the buyer approved. That mismatch stops customs clearance, stops a bank releasing payment under a letter of credit, and stops the receiving team checking the delivery against the rooms. Build the reconciliation before the container is sealed, not after it arrives.
Name who prepares each document, who checks it, and which version is final. Keep the loading photographs, the signed loading record, the inspection release and the document set in one place, because a claim for shortage or damage is decided by whether those four agree.
- Commercial invoice, with descriptions matching the approved specification
- Packing list reconciling item code, quantity, carton mark and room schedule
- Bill of lading or sea waybill, with consignee and notify party confirmed
- Certificate of origin where the destination or the payment method requires it
- Heat treatment or fumigation record and ISPM 15 marking for timber packing
- Conformity documents for regulated materials, where the destination asks for them
- One named checker and one final version before the container is sealed
Prepare the DDP Furniture Checklist
General commercial information only; tax, customs and legal treatment must be verified for the actual transaction.
Submit your project for review ↗Sources
Last reviewed: September 9, 2026. External guidance can change; verify current project requirements.
YUESHANDECODesign-led custom furniture & FF&E delivery partner in ChinaSubmit a project ↗